2018 In-House Construction Schedule

2018 In-House Construction Schedule

Project ID

Project Description

Anticipated Start Date

ROAD-0195

TWP 501 (400 m E of RR73)

May 22nd, 2018

ROAD-0171

TWP 504 (RR81 to RR82)

July 3rd, 2018

ROAD-0202

TWP 494 (HWY 22 to RR81)

August 7th, 2018

ROAD-0205

RR81 (HWY 621 to TWP 502)

September 1st, 2018

ROAD-0198

51A Ave (310 m S of 53rd Ave Lodgepole)

June 11th, 2018

Note:  Anticipated start dates are subject to weather and are dependent upon preceding project completion dates.